Banner 7
The implementation of Banner 7 is on going right now. We have targeted the following timeline for Banner 7 upgrades.
The tentative plans may change should there be any unavoidable technical issues.
BAN7: Pre-Test Environment - Oct 2005:
- Upgrade Banner 6.x to Banner 7 in Pre-Test Database - BAN7
- Technical Test - concentrates on Banner 7 baseline forms and LSU mods.
- Apps server connectivity will be tested.
- No compilation of Cobol and ProC are done and not fully working system.
PPRD: Pre-Production Development Database - March 2006:
- Upgrade Banner 6.x to Banner 7
- Comprehensive Technical testing will be done to simulate production environment. All forms (baseline & Mods),
- reports will be tested.
- Banner components in Apps server will be extensively tested.
- Each Banner module must be tested and reviewed by assigned technical users (mandatory).
- User Training
PRDN: Production Database - April 2006
|